صور الصفحة
PDF
النشر الإلكتروني

(2) Costs of added distinct work caused by the change order (e.g., new subcontract work, new prototypes, or new retrofit or backfit kits).

(3) Costs of recurring work (e.g., labor and material costs).

43.204 Administration.

(a) Change order documentation. When change orders are not forward priced, they require two documents: the change order and a supplemental agreement reflecting the resulting equitable adjustment in contract terms. If an equitable adjustment in the contract price or delivery terms or both can be agreed upon in advance, only a supplemental agreement need be issued, but administrative changes and changes issued pursuant to a clause giving the Government a unilateral right to make a change (e.g., an option clause) initially require only one document.

(b) Definitization. (1) Contracting officers shall negotiate equitable adjustments resulting from change orders in the shortest practicable time.

(2) Administrative contracting officers negotiating equitable adjustments by delegation under 42.302(b)(1), shall obtain the contracting officer's concurrence before adjusting the contract delivery schedule.

(3) Contracting offices and contract administration offices, as appropriate, shall establish suspense systems adequate to ensure accurate identification and prompt definitization of unpriced change orders.

(4) The contracting officer shall ensure that a cost analysis is made, if appropriate, under 15.805 and shall consider the contractor's segregable costs of the change, if available. If additional funds are required as a result of the change, the contracting officer shall secure the funds before making any adjustment to the contract.

(5) When the contracting officer requires a field pricing review of requests for equitable adjustment, the contracting officer shall provide a list of any significant contract events which may aid in the analysis of the request. This list should include

(i) Date and dollar amount of contract award and/or modification;

(ii) Date of submission of initial contract proposal and dollar amount;

(iii) Date of alleged delays or disruptions;

(iv) Performance dates as scheduled at date of award and/or modification; (v) Actual performance dates;

(vi) Date entitlement to an equitable adjustment was determined or contracting officer decision was rendered, if applicable;

(vii) Date of certification of the request for adjustment if certification is required; and

(viii) Dates of any pertinent Government actions or other key events during contract performance which may have an impact on the contractor's request for equitable adjustment.

(c) Complete and final equitable adjustments. To avoid subsequent controversies that may result from a supplemental agreement containing an equitable adjustment as the result of a change order, the contracting officer should

(1) Ensure that all elements of the equitable adjustment have been presented and resolved; and

(2) Include, in the supplemental agreement, a release similar to the following:

CONTRACTOR'S STATEMENT OF

RELEASE

In consideration of the modification(s) agreed to herein as complete equitable adjustments for the Contractor's..........(describe).......... "proposal(s) for adjustment," the Contractor hereby releases the Government from any and all liability under this contract for further equitable adjustments attributable to such facts or circumstances giving rise to the "proposal(s) for adjustment" (except for ..........).

[48 FR 42386, Sept. 19, 1983, as amended at 56 FR 15154, Apr. 15, 1991]

43.205 Contract clauses.

(a) (1) The contracting officer shall insert the clause at 52.243-1, ChangesFixed-Price, in solicitations and contracts when a fixed-price contract for supplies is contemplated.

(2) If the requirement is for services, other than architect-engineer or other professional services, and no supplies are to be furnished, the contracting officer shall use the clause with its Alternate I.

(3) If the requirement is for services (other than architect-engineer services, transportation, or research and development) and supplies are to be furnished, the contracting officer shall use the clause with its Alternate II.

(4) If the requirement is for architect-engineer or other professional services, the contracting officer shall use the clause with its Alternate III.

(5) If the requirement is for transportation services, the contracting officer shall use the clause with its Alternate IV.

(6) If it is desired to include the clause in solicitations and contracts when a research and development contract is contemplated, the contracting officer shall use the clause with its Alternate V.

(b)(1) The contracting officer shall insert the clause at 52.243-2, ChangesCost-Reimbursement, in solicitations and contracts when a cost-reimbursement contract for supplies is contemplated.

(2) If the requirement is for services and no supplies are to be furnished, the contracting officer shall use the clause with its Alternate I.

(3) If the requirement is for services and supplies are to be furnished, the contracting officer shall use the clause with its Alternate II.

(4) If the requirement is for construction, the contracting officer shall use the clause with its Alternate III.

(5) If a facilities contract is contemplated, the contracting officer shall use the clause with its Alternate IV.

(6) If it is desired to include the clause in solicitations and contracts when a research and development contract is contemplated, the contracting officer shall use the clause with its Alternate V.

(c) The contracting officer shall insert the clause at 52.243-3, ChangesTime-and-Materials or Labor-Hours, in solicitations and contracts when time-and-materials or labor-hour contract is contemplated.

a

(d) The contracting officer shall insert the clause at 52.243-4, Changes, in solicitations and contracts for (1) dismantling, demolition, or removal of improvements; and (2) construction, when a fixed-price contract is contemplated and the contract amount is

expected to exceed the simplified acquisition threshold.

(e) The contracting officer shall insert the clause at 52.243-5, Changes and Changed Conditions, in solicitations and contracts for construction, when the contract amount is not expected to exceed the simplified acquisition threshold.

(f) The contracting officer may insert a clause, substantially the same as the clause at 52.243-6, Change Order Accounting, in solicitations and contracts for supply and research and development contracts of significant technical complexity, if numerous changes are anticipated. The clause may be included in solicitations and contracts for construction if deemed appropriate by the contracting officer.

[48 FR 42386, Sept. 19, 1983, as amended at 56 FR 15154, Apr. 15, 1991; 60 FR 34760, July 3, 1995; 61 FR 39190, July 26, 1996]

[blocks in formation]

(a) (1) The Standard Form 30 (SF 30), Amendment of Solicitation/Modification of Contract, shall (except for the options stated in 43.301(a)(2)) be used for

(i) Any amendment to a solicitation; (ii) Change orders issued under the Changes clause of the contract;

(iii) Any other unilateral contract modification issued under a contract clause authorizing such modification without the consent of the contractor;

(iv) Administrative changes such as the correction of typographical mistakes, changes in the paying office, and changes in accounting and appropriation data;

(v) Supplemental agreements (see 43.103); and

(vi) Removal, reinstatement, or addition of funds to a contract.

(2) The SF 30 may be used for (i) modifications that change the price of contracts for the acquisition of petroleum as a result of economic price adjustment, (ii) termination notices, and (iii) purchase order modifications as specified in 13.503.

(3) If it is anticipated that a change will result in a price change, the estimated amount of the price change shall

[blocks in formation]

44.000 Scope of part.

This part prescribes policies and procedures for consent to subcontracts and for review, evaluation, and approval of contractors' purchasing systems.

Subpart 44.1-General

44.101 Definitions.

Approved purchasing system means a contractor's purchasing system that has been reviewed and approved in accordance with this part.

Consent to subcontract means the contracting officer's written consent for the prime contractor to enter into a particular subcontract.

Contractor, as used in this part, means the total contractor organization or a separate entity of it, such as an affiliate, division, or plant, that performs its own purchasing.

Contractor purchasing system review (CPSR) means the complete evaluation of a contractor's purchasing of material and services, subcontracting, and subcontract management from development of the requirement through completion of subcontract perform

ance.

Facilities (see 45.301).

Subcontract, as used in this part, means any contract as defined in subpart 2.1 entered into by a subcontractor to furnish supplies or services for performance of a prime contract or a subcontract. It includes but is not limited to purchase orders, and changes and modifications to purchase orders.

Subcontractor, as used in this part, means any supplier, distributor, vendor, or firm that furnishes supplies or services to or for a prime contractor or another subcontractor.

[48 FR 42388, Sept. 19, 1983, as amended at 50 FR 26903, June 28, 1985]

44.102 Policy.

(a) Consent to subcontracts is required under 44.201 when the subcontract work is complex, the dollar value is substantial, or the Government's interest is not adequately protected by competition and the type of prime contract or subcontract.

(b) Consent requirements may be waived when the contractor's purchasing system has been reviewed and approved in accordance with subpart 44.3.

Subpart 44.2-Consent to Subcontracts

44.201 Consent requirements.

44.201-1 Fixed-price prime contracts.

(a) Consent to subcontracts is not required under prime contracts that are firm-fixed-price or fixed-price with economic price adjustment provisions. (See paragraph (c) below for unpriced modifications.)

(b) If the contractor has an approved purchasing system—

(1) Consent to subcontracts is not required under other fixed-price prime contracts (but see paragraph (b)(2) of this section); and

(2) Consent is required for subcontracts identified in the subcontracts clause of the contract. These can be subcontracts for critical systems, subsystems, or components, or other subcontracts selected by the contracting officer as needing special surveillance. Subcontracts may be identified by subcontract number or by class of items (e.g., subcontracts for engines on a prime contract for airframes).

(c) If the contractor does not have an approved purchasing system, consent to the subcontracts specified in paragraph (d) below is required—

(1) Under fixed-price incentive and fixed-price redeterminable prime contracts; and

(2) Under prime contracts that are firm-fixed-price or fixed-price with economic price adjustment provisions, only when a new subcontract results from an unpriced modification to the prime contract.

(d) Under prime contracts required to include the clause at 52.244-1, Subcontracts (Fixed-Price Contracts), consent is required under paragraph (c) of this subsection for any subcontract that is

(1) Estimated to be over $100,000 (or less if the contract clause has been modified as permitted by its preface);

or

(2) One of a number of subcontracts, under the prime contract, with a single subcontractor for the same or related supplies or services, which in the aggregate are estimated to be over $100,000 (or less, if the contract clause has been modified as permitted by its preface).

[48 FR 42388, Sept. 19, 1983, as amended at 51 FR 36972, Oct. 16, 1986; 56 FR 15154, Apr. 15, 1991; 59 FR 67052, Dec. 28, 1994]

44.201-2 Cost-reimbursement and letter prime contracts.

(a) Consent is required under cost-reimbursement and letter prime contracts (except facilities contracts) for subcontracts (1) for fabrication, purchase, rental, installation, or other acquisition of special test equipment valued at more than $25,000 or of any items of facilities, or (2) that have experimental, developmental, or research work as one of their purposes.

(b) If the contractor does not have an approved purchasing system, consent is also required, under cost-reimbursement and letter prime contracts for (1) cost-reimbursement, time-and-mate

rials, or labor-hour subcontracts and (2) fixed-price subcontracts that exceed either $25,000 or 5 percent of the total estimated cost of the prime contract; except that for DoD, Coast Guard, and NASA, the amounts shall be the greater of the simplified acquisition threshold or 5 percent of the total estimated cost of the prime contract.

(c) If the contractor has an approved purchasing system

(1) Consent is not required for the subcontracts identified in paragraph (b) of this section (but see paragraph (c)(2) of this section). However, advance notification is still required by 10 U.S.C. 2306(e) or 41 U.S.C. 254(b); and (2) Consent is required for subcontracts identified in the subcontracts clause of the contract. These can be subcontracts for critical systems, subsystems, or components, or other subcontracts selected by the contracting officer as needing special surveillance. Subcontracts may be identified by subcontract number or by class

of items (e.g., subcontracts for engines on a prime contract for airframes).

[48 FR 42388, Sept. 19, 1983, as amended at 50 FR 1745, Jan. 11, 1985; 50 FR 26903, June 28, 1985; 50 FR 52429, Dec. 23, 1985; 59 FR 67052, Dec. 28, 1994; 60 FR 34760, July 3, 1995; 61 FR 2642, Jan. 26, 1996; 61 FR 39190, July 26, 1996] 44.201-3 Other prime contracts.

Except for purchase of raw material or commercial stock items, consent is required for all subcontracts under time-and-material contracts. Consent is required for subcontracts under prime contracts for

(a) Architect-engineer services; and

(b) Mortuary services, refuse service, or shipment and storage of personal property, when an agency requires prior approval of subcontractors' facilities.

44.201-4 Contractor use of Government sources.

The contracting officer's written authorization for the contractor to purchase from Government sources (see part 51) constitutes consent.

44.202 Contracting officer's evaluation.

44.202-1 Responsibilities.

(a) The cognizant administrative contracting officer (ACO) is responsible for consent to subcontracts, except when the contracting officer retains the contract for administration or withholds the consent responsibility from delegation to the ACO. In such cases, the contract administration office should assist the contracting office in its evaluation as requested.

(b) The responsible contracting officer shall

(1) Promptly evaluate the contractor's requests for consent to subcontract;

(2) Obtain assistance in the evaluation from subcontracting, audit, pricing, technical, or other specialists as necessary; and

(3) Notify the contractor in writing of consent or the withholding of consent, including any changes or corrections required.

(c) Designation of a specific subcontractor by the Government or evaluation of subcontracts during contract

negotiations does not in itself satisfy the requirements for advance notification or consent pursuant to the clauses at 52.244-1, 52.244-2, and 52.244-3. However, if, in the opinion of the contracting officer, the advance notification or consent requirements were satisfied for certain subcontracts evaluated during negotiations, the contracting officer shall include a statement in the contract that those requirements have been satisfied. The statement shall identify the specific subcontracts and contain appropriate information concerning the extent to which such requirements are satisfied and/or limited with respect to future changes or revisions in work statement, specifications, or other applicable aspects of the contract that may be subject to change. For fixed-price contracts see 44.204(a)(3).

[48 FR 42388, Sept. 19, 1983, as amended at 55 FR 52796, Dec. 21, 1990]

44.202-2 Considerations.

(a) The contracting officer responsible for consent shall review the request and supporting data and consider the following:

(1) Is the decision to subcontract consistent with the contractor's approved make-or-buy program, if any (see subpart 15.7)?

(2) Is the subcontract for special test equipment or facilities that are available from Government sources (see subpart 45.3)?

(3) Is the selection of the particular supplies, equipment, or services technically justified?

(4) Has the contractor complied with the prime contract requirements regarding small business subcontracting, including, if applicable, its plan for subcontracting with small, small disadvantaged and women-owned small business concerns (see part 19)?

(5) Was adequate price competition obtained or its absence properly justified?

(6) Did the contractor adequately assess and dispose of subcontractors' alternate proposals, if offered?

(7) Does the contractor have a sound basis for selecting and determining the responsibility of the particular subcontractor?

« السابقةمتابعة »